Work on the traffic signal at Highway 100 concluded Friday afternoon marking the opening of Bluff Road to traffic.

Motorists are permitted on the roadway, however final construction needs to be completed next week. People should be aware that construction equipment still is on the scene. 

The scope of work included a 4-inch asphalt overlay from Highway 100 to the north city limits, improving of the grade condition by elevating the road north of the approach to Highway 100, and adding a right-turn lane from Bluff Road onto westbound Highway 100.

The work also added safety improvements with 2-foot shoulders and guardrails along a portion of the road north of Highway 100, and relocation of MoDOT and an Ameren light pole.