Washington Council Awards Contract for Multi-Street Project

Print
Font Size:
Default font size
Larger font size

Posted: Wednesday, February 6, 2013 8:00 pm

Four bids for a multi-street resurfacing project in Washington came in below the engineer’s estimate.

City council members Monday night approved an ordinance awarding the contract to N.B. West Contracting Co. Inc., which quoted a price of $531,402.22.

City Engineer Dan Boyce said the engineer’s estimate for the work was $657,535.80.

Boyce said the next step is to get approval of the contract from Missouri Department of Transportation. After MoDOT concurs, a pre-construction conference will be held with the contractor.

The project includes resurfacing International Avenue, Rabbit Trail Drive, Wenona Drive, Lexington Lane and Washington Heights Drive and installation of sidewalks in some areas. Curb repair and correcting a stormwater problem on Lexington Lane also are part of the project.

The work is expected to be done this spring and summer.

A federal grant obtained through the East-West Gateway Council of Governments (EWGW) will pay about 75 percent of the total costs.

The original project proposed under the federal Transportation Improvement Program for the St. Louis region called for sidewalks to be added along all the streets, but after residents raised objections, the city removed proposed sidewalks along Wenona Drive, Lexington Lane and Washington Heights Drive from the project.

The plan calls for 5-foot-wide sidewalks along the following areas:

• East side of International Avenue between Highway 100 north to the Burger Park entrance;

• West side of Rabbit Trail Drive between the two entrances to the Bank of Franklin County property; and

• East side of Rabbit Trail Drive from Highway 100 to the entrance to the Phoenix Center near Cinema 1 Plus.

Also in the plan is work to help alleviate stormwater drainage issues near Lexington Lane and Monticello Drive.

Other companies that submitted bids were:

Pace Construction Company, $532,500; Magruder Paving LLC, $537,843.24; Krupp Construction, $624,288.48; and Gershenson Construction Co., $678,972.08.

/local_news/communities/washington
(%remaining%) Remaining Thanks for visiting The Missourian. You're entitled to view 20 free articles every 30 days. Then, if you enjoy our site and want full access, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining Thanks for visiting The Missourian. You're entitled to view 20 free articles every 30 days, and you currently have (%remaining%) remaining. Then, if you enjoy our site and want full access, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining We hope you will enjoy this free article on The Missourian. You're entitled to view 20 free articles every 30 days, and you currently have (%remaining%) remaining. Then, if you enjoy our site and want full access, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining We hope you will enjoy this free article on The Missourian. You're entitled to view 20 free articles every 30 days, and you currently have (%remaining%) remaining. Then, if you enjoy our site and want full access, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining Thank you for reading The Missourian. You have viewed (%remaining%) of your 20 free pages in 30 days. Please login or register at this time and enjoy the next (%remaining%) articles free of charge. After your 20 free articles, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining Thank you for reading The Missourian. Because you have already viewed this article, you may view it again as many times as you would like without subtracting from your remaining free article views.
(%remaining%) Remaining Thank you for registering on The Missourian. You're entitled to view 20 articles for free every 30 days, and you currently have (%remaining%) remaining. Then, if you enjoy our site and want full access, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining Thank you for reading The Missourian. You're entitled to view 20 articles for free every 30 days, and you currently have (%remaining%) remaining. Then, if you enjoy our site and want full access, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining Thank you for reading The Missourian. You're entitled to view 20 articles for free every 30 days, and you currently have (%remaining%) remaining. Then, if you enjoy our site and want full access, we'll ask you to purchase an affordable subscription.
(%remaining%) Remaining Thank you for reading The Missourian. You're entitled to view 20 articles for free every 30 days. This is your last free article this period. On your next article we'll ask you to purchase an affordable subscription.

Featured Ads